MAIN ST CONSTRUCTION SCHEDULE
SCHEDULE FOR EAST MAIN ST, MENDHAM BORO WATER MAIN AND SERVICE REPLACEMENT PROJECT. Work Hours: 8am to 4pm.
Monday 7/26/21- Orchard St tie ins (2), Dean Rd Detour needed
Tuesday 7/27/21- Halstead Rd and Hillcrest Rd tie ins, Dean Rd Detour needed
Wednesday 7/28/21- Dean Rd tie in and (3) services, Dean Rd closed
Thursday 7/29/21- 9 Services, NO detour needed for Dean Rd
Friday 7/30/21- 9 Services, NO detour needed for Dean Rd
Monday 8/2/21- Tempewick Rd tie in & cut and cap, NO detour needed for Dean Rd
Tuesday 8/3/21- Service to nursing home plus (2) hydrant installs, NO detour needed for Dean Rd
Wednesday 8/4/21- 9 Services, NO detour needed for Dean Rd
Thursday Night 8/5/21- Kings Market Tie Ins (2), NO detour needed for Dean Rd
Friday Night 8/6/21- Medical Building service, No detour needed for Dean Rd
Monday 8/9/21- Restoration and Demobilization, No detour needed for Dean Rd
Montana will return in a few weeks to work on the sidewalk and curb restoration.
They will be back to final mill and pave the roadway according to Morris County’s requirements, which is a six-month settlement period.
Road Repaving is estimated to occur of 2022.